I am often asked what the most frequent VAT errors made by a business are. I usually reply along the lines of “a general poor understanding of VAT, considering the tax too late or just plain missing a VAT issue”. While this is unquestionably true, a little further thought results in this top ten list of VAT horrors:
So, you may ask: “How do I make sure that I avoid these VAT pitfalls?” – And you would be right to ask.
Of course, I would recommend that you engage a VAT specialist to help reduce the exposure to VAT costs!
Latest from the courts
The First-Tier tribunal (FTT) considered the case of CMJ (Aberdeen) Limited (CMJ) and whether the supply of building services in respect of the construction of a dwelling were correctly zero rated by the appellant. HMRC deemed that the construction services were standard rated on the basis that the works were not carried out in accordance with the terms of the relevant statutory planning consent.
Background
HMRC’s view was that, although planning consent was in place at the time the construction services were supplied by the appellant, that planning consent permitted only the alteration or enlargement of a dwelling and did not allow for the construction of a dwelling. HMRC accept that the property was constructed as a new building, but that this was not permitted by the planning consent and so the construction was not carried out in accordance with it.
CMJ contended that statutory planning consent had been obtained for the construction via a combination of the planning consent and a construction building warrant which it had obtained from the relevant authority, and which allowed for the construction of a new building.
Legislation
The zero rating for the construction of new dwellings is contained in The VAT Act 1994, Schedule 8, Group 5, item 2
“The supply in the course of the construction of
(a) a building designed as a dwelling…”
Note 2 to Group 5 of Schedule 8 to the VAT Act include the following:
“(2) A building is designed as a dwelling or a number of dwellings where in relation to each dwelling the following conditions are satisfied…
…(d) statutory planning consent has been granted in respect of that dwelling and its construction or conversion has been carried out in accordance with that consent.
Decision
The appeal was dismissed. It was judged that the building warrant did not comprise statutory planning consent for the purposes of note 2 (d) because:
It was not possible to carry out works of construction in accordance with a valid statutory consent, since no such consent had been given for construction at the time that the building works were carried out.
Commentary
The legislation covering building work is complex and there are many traps for the unwary. Even the seemingly straightforward matter of whether a new dwelling is constructed can produce difficulties, as in this case. We always counsel that proper VAT advice is sought in such circumstances.